Back to Pipeline
PRO-2026-0007BLOCKEDPermitting

Amanda Davis

Houston, TX9.8 kW$33,60052d in pipeline
Customer Portal

Stage Progress

Lead
Qualified
Proposal Sent
Contract Signed
Engineering
Procurement
Permitting
Interconnection
Crew Scheduled
Installation
Inspection
PTO
Handoff
Completed

Milestones

8/11

Initial contact

LeadJan 25, 2026by Cole Wagstaff

Utility bill reviewed

QualifiedJan 28, 2026by Cole Wagstaff

Roof assessment passed

QualifiedJan 30, 2026by Cole Wagstaff

Proposal generated

Proposal SentFeb 2, 2026by Cole Wagstaff

Contract executed

Contract SignedFeb 5, 2026by Cole Wagstaff

Site survey completed

EngineeringFeb 8, 2026by Randy Garn

System design finalized

EngineeringFeb 12, 2026by Randy Garn

Permit submitted

PermittingFeb 15, 2026by Randy Garn

HOA approval obtained

Permitting

Tree survey completed

Permitting

Permit revision resubmitted

Permitting

Notes

Randy GarnMar 12, 2026Permitting

Houston permit office returned application — requires HOA approval letter and tree survey before resubmission. HOA meeting not until April 2nd. This is our bottleneck.

Cole WagstaffMar 13, 2026Permitting

Called homeowner to explain delay. She understands and is working with HOA. Needs tree survey vendor — recommending ArborPro Houston.

Project Details

Sales Rep
Cole Wagstaff
Project Manager
Randy Garn
Financing
TPO LEASE
Panels
24
Est. Production
15,680 kWh/yr

Homeowner

Email
amanda.d@email.com
Phone
713-555-0707
Utility
CenterPoint Energy
Avg Bill
$345/mo
Roof
asphalt shingle
Credit
750-799
Source
web

Permits

City of Houston, TXREVISION REQUIRED