Back to PipelineCustomer Portal
PRO-2026-0004ON TRACKInstallation
David Thompson
Orlando, FL9.2 kW$31,50072d in pipeline
Stage Progress
Lead
Qualified
Proposal Sent
Contract Signed
Engineering
Procurement
Permitting
Interconnection
Crew Scheduled
Installation
Inspection
PTO
Handoff
Completed
Milestones
10/13Initial contact
LeadJan 5, 2026by Cole Wagstaff
Utility bill reviewed
QualifiedJan 8, 2026by Cole Wagstaff
Contract executed
Contract SignedJan 15, 2026by Cole Wagstaff
Site survey completed
EngineeringJan 20, 2026by Craig Stratton
System design finalized
EngineeringJan 25, 2026by Craig Stratton
Equipment ordered
ProcurementJan 28, 2026by Craig Stratton
Equipment delivered
ProcurementFeb 15, 2026by Craig Stratton
Permit approved
PermittingFeb 28, 2026by Craig Stratton
Crew mobilized
InstallationMar 18, 2026by Andre Thompson
Racking installed
InstallationMar 18, 2026by Andre Thompson
Panels mounted
Installation
Electrical connections
Installation
System commissioning
Installation
Notes
Andre ThompsonMar 18, 2026Installation
Day 1 install going well. Racking complete. Starting panel mount tomorrow morning. Weather looks clear.
Project Details
- Sales Rep
- Cole Wagstaff
- Project Manager
- Craig Stratton
- Install Crew
- Orlando Team
- Financing
- TPO LEASE
- Panels
- 22
- Est. Production
- 14,720 kWh/yr
- Scheduled Install
- Mar 18, 2026
Homeowner
- david.t@email.com
- Phone
- 407-555-0404
- Utility
- OUC
- Avg Bill
- $278/mo
- Roof
- asphalt shingle
- Credit
- 700-749
- Source
- web
Permits
City of Orlando, FLAPPROVED
#BP-2026-SOL-088