Back to Pipeline
PRO-2026-0003ON TRACKInspection

Jennifer Garcia

Scottsdale, AZ12 kW$42,00093d in pipeline
Customer Portal

Stage Progress

Lead
Qualified
Proposal Sent
Contract Signed
Engineering
Procurement
Permitting
Interconnection
Crew Scheduled
Installation
Inspection
PTO
Handoff
Completed

Project Details

Sales Rep
Maria Santos
Project Manager
Randy Garn
Install Crew
Phoenix Solar Team
Financing
CASH
Panels
28
Est. Production
21,600 kWh/yr
Scheduled Install
Mar 1, 2026
Actual Install
Mar 1, 2026

Homeowner

Email
jen.garcia@email.com
Phone
480-555-0303
Utility
APS
Avg Bill
$385/mo
Roof
tile
Credit
800+
Source
D2D

Permits

City of Scottsdale, AZAPPROVED
#SOL-2026-0334