Back to PipelineCustomer Portal
PRO-2026-0002ON TRACKPTO
Marcus Johnson
Austin, TX10.5 kW$34,20098d in pipeline
Stage Progress
Lead
Qualified
Proposal Sent
Contract Signed
Engineering
Procurement
Permitting
Interconnection
Crew Scheduled
Installation
Inspection
PTO
Handoff
Completed
Notes
Craig StrattonMar 15, 2026PTO
Austin Energy PTO application submitted. Typically 2-3 weeks for this utility. Homeowner eager to activate.
Project Details
- Sales Rep
- Jake Simmons
- Project Manager
- Craig Stratton
- Install Crew
- Austin Crew 1
- Financing
- TPO PPA
- Panels
- 25
- Est. Production
- 16,800 kWh/yr
- Scheduled Install
- Feb 20, 2026
- Actual Install
- Feb 20, 2026
Homeowner
- marcus.j@email.com
- Phone
- 512-555-0202
- Utility
- Austin Energy
- Avg Bill
- $312/mo
- Roof
- asphalt shingle
- Credit
- 700-749
- Source
- web
Permits
City of Austin, TXAPPROVED
SolarAPP+ Enabled
#SP-2026-1102